چک لیست بازرسی انواع تابلو های برق .. خیلی کاربردی و با خلاقیت خودم جمع اوری شده
| INSPECTION CHECK LIST FOR ELECTRICAL PANEL LV/MV | ||
| item | Test Discriptions | APPROVED |
| 1 | 1)Visual Inspection | |
| 2 | 1-1) Dimension control | |
| 3 | Width, Height, Deep | |
| 4 | Dimension panel gland plate | |
| 5 | Control fixing point panel to floor of switchgear room | |
| 6 | 2-1) Painting control | |
| 7 | Painting thickness that shall be bigger than 70 micrometer less than 120 | |
| 8 | Check damaged or scratch on panel painting | |
| 9 | Check shade or two paint on panel painting | |
| 10 | Comparing RAL of painting with requested | |
| 11 | 3-1) Bus bar control | |
| 12 | Bus bar size | |
| 13 | Bus bar connection | |
| 14 | Phase sequence with colored labels | |
| 15 | Bus bar resistance and insulators | |
| 16 | Distance between phase/ phase, phase / earth | |
| 17 | Heat shrine on bus bar for insulation not happened damaged | |
| 18 | Painting on bus bar no happened damaged or scratch on it | |
| 19 | 4-1) Mechanical control | |
| 20 | Opened and closed all door’s panel | |
| 21 | Easy Rack In/Out CB or Feeder | |
| 22 | Check Earth switch/Earth bus | |
| 23 | key Lock /casel key | |
| 24 | Interlock between the door and CB | |
| 25 | Electro Magnet interlock for earth switch | |
| 26 | Screw and nut tightening torque values for EX: Screw Type M10 /40 NM | |
| 27 | 5-1) Part list control | |
| 28 | Technical Specifications electrical | |
| 29 | Brand of electrical and mechanical equipment | |
| 30 | Quantity of electrical and mechanical equipment | |
| 31 | 6-1) Front view Panel | |
| 32 | Control view digram with Panel | |
| 33 | 2) Electrical Test | |
| 34 | 1-2) wiring control | |
| 35 | All wire and cable with wire & cable show | |
| 36 | All wire number in two heads | |
| 37 | All tightened in terminals | |
| 38 | All terminal number | |
| 39 | All wire size | |
| 40 | All electrical equipment Tag | |
| 41 | All doors shall be earthed to panel main structure | |
| 42 | All signals colors and description |
|
| 43 | All feeder name | |
| 44 | 2-2) Functional test | |
| 45 | All circuit shall be tested | |
| 46 | Check the transmissions contacts and signal to or of outside panel | |
| 47 | Check the correct operation lighting signal on panel door | |
| 48 | Check the correct operation lighting and space heater and force ventilation | |
| 49 | 3-2) Protections and Measuring Equipment Test | |
| 50 | 1-3-2) Secondary current Protection relay | |
| 51 | Test the correct operation ratio of CT | |
| 52 | Test the correct operation ratio of core balance | |
| 53 | Test the trip circuit operation TCS relay | |
| 54 | Current test block test | |
| 55 | 2-3-2) Secondary Voltage Protection relay test | |
| 56 | Test the correct operation ratio of PT | |
| 57 | Voltage test block test | |
| 58 | 3-3-3) built in protection relay in CB | |
| 59 | Inject voltage and current to CB | |
| 60 | 3-3-4)Porotection relay or Transducer test | |
| 61 | Multi function relay /49/50/51N/86/76/.. | |
| 62 | RTD cotroler test | |
| 63 | Current Transducer | |
| 64 | Voltage Transducer | |
| 65 | 4-2) Dielectric tests | |
| 66 | 1-4-2) Main circuit Megger test before Power frequency test/In Low voltage Panel with 1 KV DC in duration 1 minute ,shall be bigger than 5M ohme for each phase L1 with L2, L3, N, PE /L2 with L1, L3, N, PE/L3 with L1, L2, N, PE/N with L1, L2, L3, PE | |
| 67 | 2-4-2) Main circuit power frequency Test/injection 2.5KV – 50HZ for60 Sec .For switchgear rated insulation level 0.69 KV/for example :in Medium voltage injection 50KV – 50HZ for 60 Sec .For switchgear rated insulation level 24 KV ,Note:approving the report of test need no happen Arc in duration test | |
| 68 | 3-4-2) Main circuit Megger test After Power frequency test In Low voltage Panel according IEC61439-1/IEC 60947 standard with 1 kVDC in duration 1 minute,5M ohme/In Medium voltage panel with 5 KV DC in duration 1 minute , shall be bigger than 10 M ohm | |
| Note | For the Dielectric tests shall be all main CB rack in and closed and all PT and Surge arrester disconnected and all current circuit out put of secondary CT shall be closed | |
| تهیه شده توسط مهندس محسن خدابخشی -شرکت آریا بهین افروز RSTNE@CHMAIL.IR | ||
+ نوشته شده در یکشنبه سیزدهم بهمن ۱۳۹۲ ساعت 11:5 توسط محسن خدابخشی
|
محسن خدابخشی کارشناس برق قدرت و کارشناس ارشد مدیریت اجرایی 09125348620